Part H - General provisions

H1. Contract variation

H1.1 Subject to clause H1.2, no variation or modification to the Contract is valid unless it is in writing and signed by the Council and the Contractor.

H1.2 The Council shall be entitled to issue to the Contractor in writing or, in case of urgency orally (provided the Council confirms oral instructions in writing as soon as it is practicable), variation orders requiring the addition, suspension, reduction or cessation of provision of any services and the provision of emergency services in accordance with revised delivery instructions. The Contractor shall charge for the impact of the variation order in accordance with the rates and prices used to calculate the price.

H2. Third party rights

H2.1 This Contract is enforceable by the original parties to it, by their successors in title and permitted assignees. Any rights of any person to enforce the terms of this Contract pursuant to The Contracts (Rights of Third Parties) Act 1999 are excluded.

H3. No waiver

H3.1 Failure by either party at any time to enforce any one or more of the provisions of this Contract or to require performance by the other party of any of the provisions shall not constitute or be construed as a waiver of the provision or of the right at any time subsequently to enforce all terms and conditions of this Contract nor affect the validity of the Contract or any part of it or the right of the parties to enforce any provision in accordance with its terms.

H3.2 No waiver of any of the provisions of this Contract shall be effective unless it is expressed to be a waiver in writing and communicated in accordance with clause A3.

H4. Severance

H4.1 If any provision of the Contract shall become or shall be declared by any court of competent jurisdiction to be invalid or unenforceable in any way, such invalidity shall not impair or affect any other provision all of which shall remain in full force and effect.

H5. Assignment, sub-contracting and responsibility

H5.1 Subject to any express provision of this Contract, the Contractor shall not without the prior written consent of the Council, assign all or any benefit, right or interest under this Contract or sub-contract the provision of the services.

H5.2 The Council shall be entitled to:

H5.2.1 assign, novate or otherwise dispose of its rights and obligations under this Contract, in whole or in part, to any contracting authority (as defined in section 2 of the PA 2023) without the prior consent of the Contractor

H5.2.2 transfer, assign or novate its rights and obligations where required by law

H5.3 The Contractor shall remain responsible and liable for the acts and omissions of any other members of a consortium arrangement, sub-contractors, servant, agent and employee as though they were its own.

H5.4 Subject to clause H5.1 where the Contractor enters into a Sub-Contract, the Contractor shall include in that Sub-Contract

H5.4.1 provisions having the same effect as clauses C1.3 to C1.5 of this Contract

H5.4.2 a provision requiring the counterparty to that Sub-Contract to include in any Sub-Contract which it awards provisions having the same effect as clauses C1.3 to C1.5 of this Contract

 

H6. Force majeure

H6.1 Neither party shall be liable for failure to perform its obligations under the Contract if such failure results from force majeure.

H6.2 If the Council or the delivery location is affected by circumstance of force majeure, the Council shall be entitled to, totally or partially, suspend the date or dates for delivery of the services until the circumstances of the force majeure have ceased. The suspension shall not give rise to any claim by the Contractor against the Council nor entitle the Contractor to terminate the Contract.

H6.3 Industrial action by, or illness or shortage of the Contractor's staff, agents or subcontractors, failure or delay by any of the Contractor's suppliers to supply goods, components, services or materials and breach of the Contractor's warranties under clause B6 (Warranty) shall not be regarded as an event of force majeure.

H6.4 If the event of force majeure continues for more than two months either party may give written notice to the other to terminate the Contract immediately or on a set termination date.

H6.5 If the Contract is terminated in accordance with clause H6.4 neither party will have any liability to the other except that any rights and liabilities which accrued prior to termination will continue to exist.

H7. Inducements

H7.1 The Contractor shall not offer or give, or agree to give, to any employee, agent, servant or representative of the Council any gift or consideration of any kind as an inducement or reward for doing, any act in relation to the obtaining or execution of the Contract or any other contract with the Council, or for showing or refraining from showing favour or disfavour to any person in relation to the Contract or any such contract. The attention of the Contractor is drawn to the criminal offences under the Prevention of Corruption Acts 1889 to 1916.

H7.2 The Contractor warrants that it has not paid commission nor agreed to pay any commission to any employee or representative of the Council by the Contractor or on the Contractor's behalf.

H7.3 Where the Contractor engages in conduct prohibited by clauses H7.1 and H7.2 in relation to this or any other contract with the Council, the Council has the right to:

H7.3.1 terminate the Contract and recover from the Contractor the amount of any loss suffered by the Council resulting from the termination, including the cost reasonably incurred by the Council of making other arrangements for the provision of the Services and any additional expenditure incurred by the Council throughout the remainder of the Contract Period

H7.3.2 recover in full from the Contractor any other loss sustained by the Council in consequence of any breach of this clause whether or not the Contract has been terminated

 

H8. Costs and expenses

H8.1 Each of the parties will pay their own costs and expenses incurred in connection with the negotiation, preparation, execution, completion and implementation of this Contract.

H9. No agency or partnership

H9.1 Nothing contained in this Contract, and no action taken by the parties pursuant to this Contract, will be deemed to constitute a relationship between the parties of partnership, joint venture, principal and agent or employer and employee. Neither party has, nor may it represent that it has, any authority to act or make any commitments on the other party's behalf.

H10. Non solicitation and offers of employment

H10.1 The Contractor agrees that it will not, without the prior written consent of the Council, whether directly or indirectly, and whether alone or in conjunction with, or on behalf of, any other person and whether as a principal, shareholder, director, employee, agent, consultant, partner or otherwise during the contract period or for a period of 12 months following termination of this Contract:

H10.1.1 solicit or entice, or endeavour to solicit or entice, away from the Council, any person directly related to the services employed in a senior capacity in a managerial, supervisory, technical, sales or administrative capacity by, or who is or was a consultant to, the Council at the date of the termination of this Contract or at any time during the period of one month immediately preceding the date of termination

H10.1.2 attempt, or knowingly assist or procure any other person to do the above

 

H11. Inspection of contractor's premises

H11.1 The Contractor shall permit the Council to make any inspections or tests which may reasonably be required in respect of the Contractor's premises in relation to the Contract.

H12. Law and jurisdiction

H12.1 This Contract shall be governed by the laws of England and shall be subject to the exclusive jurisdiction of the English courts.