Tuesday, 20 September 2011
Leven Bridge-Repair Strategy
Cabinet was advised of the issues that had forced the closure of the road
going over Leven Bridge.
It was explained that the visible cracking in the road surface at Leven
Bridge prompted a road closure in February 2010. The intervening period
since then had resulted in a number of investigations being carried out to
determine the cause and assist in identifying the solution. These
investigations had found that scour in the river bed and river bank had
undermined the upstream corner of the north road bridge abutment and
footbridge abutment resulting in a partial lack of support to both the road
bridge and footbridge.
Remedial measures had been identified that involved filling the void with
special grout bags and reinstating the river bed with anti scour material
that would prevent the problem re-occurring. These were being implemented.
An appropriate contractor was appointed on an emergency basis to assist
with the development and delivery of the solution. In parallel officers had
been working closely with the Environment Agency, utility companies and
landowners to secure the necessary consents to ensure the works could be
expedited at the earliest convenience.
It was anticipated that the works should be completed in July 2010 and the
bridge re-opened to traffic in that period.
Officers were working closely with the contractor and other agencies to
ensure that the cost implications in implementing the project were kept to
a minimum, but it was recognised that the extent of works that were
required could be up to £500,000. The Acting Head of Technical Services had
been in dialogue with Government Office North East and the Department of
Transport since early March to try and source financial support for the
situation. Mixed messages had been received however, it was the intention
to continue to lobby at the highest level to try and secure the support
that was rightly needed to fund the project. The Cabinet Member for
Regeneration and Transport had also written to the Secretary of State for
Transport to strengthen this message. Cabinet noted that, where possible,
and appropriate, officers would pursue other potential sources of funding
where liability was proven to be a significant contributory factor to the
damage to the bridge. This may be in the form of a cocktail of
contributions based upon where the liability sat and the level of
contribution to the overall problem. It was recognised however that the
provisions within the new Flood and Water Management Act which received
Royal assent in April 2010 in respect of defining responsibilities for
maintenance of flood defence assets would not be able to be applied
retrospectively.
The closure of the bridge and the arterial route it carries had had an
impact not only on local residents and commuters but also local businesses
in the immediate vicinity including those in Yarm, Ingleby Barwick and
Thornaby. Throughout the period officers had given regular updates to Ward
Councillors and to the wider public through dialogue with the media.
Officers would continue to ensure that the progress and completion of the
project was effectively communicated.
For further details regarding the Council's plans to address the damage
caused to the Borough's roads by the recent bad weather, contact Russell
Smith, tel. 01642 526935; e-mail
Russell.Smith@stockton.gov.uk.
Supply of Primary School Places Across the Borough
Cabinet heard details of how between 1999 and 2009 the number of primary
school pupils in the borough had fallen by almost 3,000. During that time
the pupil capacity of many primary schools was reduced, and 1,700 places
were removed in order to maintain the level of unfilled places at around
10% overall.
The latest projections (based on January 2010 data) show a rising trend in
the number of pupils of primary school age in the borough beginning in
September 2010 and continuing for at least four years.
It now seems likely that pupil numbers will rise more rapidly than
projected last year. The number of applications for reception places in
September 2010 was over 100 greater than projected. In some areas of the
borough there will be very few vacant reception places in September. There
is now a need to identify options for increasing capacity in those areas of
the borough for 2011 and beyond, and to consider how those options might be
funded.
In all areas of the borough the number of pupils attending Catholic schools
is projected to increase beyond present capacity. It would therefore be
necessary to discuss possible options with the two Catholic dioceses.
A further report containing options that could be developed to ensure a
sufficient supply of places in all areas of the Borough taking into account
the availability of resources, would be presented to a meeting of Cabinet
later in the year.
Further details regarding the above can be obtained by contacting Tony
Beckwith, Head of Support Services, tel. 01642 527052; e-mail
Tony.Beckwith@stockton.gov.uk
Health & Wellbeing Strategy for Stockton on Tees
Finally, Cabinet received and endorsed a Health and Wellbeing Strategy for Stockton on Tees; which had been developed by the Council and its partners to improve the health and wellbeing of families and communities and adults in the Borough by tackling health inequalities and focusing on the following key priorities:-
- Mental Health
- Alcohol
- Obesity
- Smoking
- Health Inequalities
- Sexual Health
Copies of the strategy can be obtained by contacting Ruth Hill, Assistant Director of Health Improvement, tel. 01642 352354; e-mail Ruth.Hill@northteespct.nhs.uk
If you wish to comment on any of the decisions made by Cabinet above; or find out more about any of the issues discussed, please send messages and information requests to Democratic Services where staff will be pleased to hear from you. Democratic Services, Stockton-on-Tees Borough Council, Law & Democracy, Municipal Buildings, Church Road, Stockton-on-Tees TS18 1LD. Tel: 01642 528173 Fax: 01642 528162 Email: DemocraticServices@stockton.gov.uk.
