Holme House Road, Stockton

The Portrack Lane & Holme House Road Improvement Works started on 26th January 2009. The works included the following:

  • Widening of Holme House Road between the existing 'Big W' access and Portrack Lane
  • Construction of a new puffin crossing on Portrack Lane between 'Big W' and Asda
  • Construction of a new puffin crossing on Marston Road
  • Construction of two new low floor bus stops on Portrack Lane

Works were scheduled to last 12 weeks and were carried out by Sillars (B&CE) Ltd.

The works were completed 1st April 2009.

Page last updated 11/02/10.