Timeline
February 2008 Cabinet & Council approved proposals for £15million refurbishment
February-June 2008 Initial design of scheme
April 2008 Preliminary discussions held with major contractors
April - June 2008 Theatre market testing
June 2008 Negotiations with theatre preferred operator commenced
Early June 2008 Procurement Strategy and tender process finalised
Early June 2008 OJEU notice placed
Late June 2008 Sport England Bid submitted (Stage 1)
July 2008 Pre-planning discussions commenced
September - December 2008 Sport England bid (Stage 2) submitted
November 2008 Morgan Ashurst appointed as the contractor for stage one (Early Contractual Involvement)
November 2008 Detailed design and costing work starts with Morgan Ashurst
Spring 2009 Decision of Sport England Bid (Stage 2) received
Spring 2009 New theatre operator contract agreed
March 2009 Cabinet approval sought for final design & cost and to appoint contractor for stage two of the works (construction) and new theatre operator contract agreed
April 2009 Planning application submitted, and listed building consent sought
May 2009 Planning decision received
May 2009 Contractor for stage two (construction) appointed (subject to Planning & Cabinet approval)
June 2009 Detailed design and costing work completed and Forum closes on Tuesday 30th June
July 2009 Works on site have started
January 2011 Works are complete and the refurbished building reopens to the public (subject to programme)
Contact Us
Contact: Regeneration Project Manager
Louise McDonald
Municipal Buildings,
Regeneration & Economic Development,
PO Box 34,
Church Road,
Stockton-on-Tees
TS18 1LD
Tel: 01642 528942
Email:
louise.mcdonald
@stockton.gov.uk
Web Links
Stockton Council is not responsible for the content of external websites.