Mandale Scheme Update
Regeneration at Mandale Park is progressing well with our development partners, Barratt Homes and Keepmoat Homes, continuing to build new homes for sale as well as rental properties on behalf of ISOS Housing Ltd.
Phase 1a and 1
The main building work on these phases has now been completed and all new homes have been sold or let.
Phase 2
Construction of the new homes began on phase 2 in 2007, Keepmoat Homes have completed their half of the site. For information on homes for sale in this phase please contact Keepmoat Homes or Barratt Homes.
Phase 3
The relocation of residents in Phase 3 began in April 2010 and will be completed in October 2014.
Mandale Phase 3A Decant: April 2010 - October 2011
Residents from the addresses below will be moved:
1-18 Scalby Square
41-53 Scalby Square
13-24 Pickering Road
23-33 Brotton Road (odd numbers only)
Phase 3B Decant: October 2011 - March 2013
19-40 Scalby Square
6-10 Saltburn Road
1-25 Skelton Road
2-24 Skelton Road
16-38 Diamond Road
Phase 3C Decant: April 2013 - October 2014
2-14 Diamond Road
26-42 Skelton Road
27-39 Skelton Road
1-21 Brotton Road
2-26 Brotton Road
1-43 Northallerton Road
Linear Park
The new park, another feature of the redevelopment, is now complete. It includes a network of cycle ways and footpaths, art features and seating as well as two adult sized football pitches. Below you can download a plan of the park.
Should you require further information regarding any of the phases please do not hesitate to contact us.
Web Links
Stockton Council is not responsible for the content of external websites.
Additional Resources
Linear Park Plan
Mandale Phase 3 Relocation Plan
Relocation plan for phase 3 at MandaleIf you have problems accessing the Adobe PDF downloads then click here for help
Mandale Scheme Update
Contact Us